Complete play-by-play for IT setup week, event days, and teardown. Each section has detailed task lists with sign-off columns.
Event Dates: February 13–15, 2026
Location: Central Florida Fairgrounds, 4603 W Colonial Dr, Orlando, FL 32808
| Day | Date | Hours | Focus |
|---|
| Friday | Feb 13 | Gates 9 AM – 5 PM | Event Day 1 |
| Saturday | Feb 14 | Gates 9 AM – 5 PM | Event Day 2 |
| Sunday | Feb 15 | Gates 9 AM – 1 PM | Event Day 3 |
Saturday, February 7 — Storage Locker Review
Time: TBD
Crew: Mike
Review stored equipment and verify everything needed for the event is present and in good condition.
Storage Review Tasks
| Task | Done | Notes |
|---|
| Review all stored IT equipment | [ ] | |
| Verify PRInfo kits (4x TV, stand, Pi) are present | [ ] | |
| Check cables, power strips, extension cords | [ ] | |
| Verify badge printer and supplies | [ ] | |
| Check UniFi surveillance equipment | [ ] | |
| Verify Starlink equipment | [ ] | |
| Check TP-Link routers (4x) | [ ] | |
| Note any missing or damaged items | [ ] | |
| Verify supplies: alien tape, zip ties (6” & 12”) | [ ] | |
Monday, February 9 — Site Visit
Time: ~1 PM
Crew: Mike, Todd, David, Chris
Review all wired network drops and do cursory WiFi mapping for each building.
Monday — Equipment Delivery
Equipment is delivered from the storage locker Monday AM. This is a hands-off / lights-out delivery — IT does not need to be present. Items are dropped at the IT office and buildings.
- TVs and TP-Link routers → IT office
- Accessory boxes (power cords, network cables, Starlink) → IT office
- Stands → delivered to each building
Inventory will be verified on Wednesday when the crew arrives for display setup.
Network Drop Verification
| Drop Location | Present | Active | Speed OK | Notes |
|---|
| Booth 015 | [ ] | [ ] | [ ] | |
| Booth 094 | [ ] | [ ] | [ ] | |
| Booth 145 | [ ] | [ ] | [ ] | |
| Booth 152 | [ ] | [ ] | [ ] | |
| Booth 162 | [ ] | [ ] | [ ] | |
| Booth 169 | [ ] | [ ] | [ ] | |
| Booth 191 (Prize & Info) | [ ] | [ ] | [ ] | |
| Booth 220 | [ ] | [ ] | [ ] | |
| IT Office | [ ] | [ ] | [ ] | |
| Badge Booth | [ ] | [ ] | [ ] | |
WiFi Mapping
| Building | Signal Quality | AP Needed? | Notes |
|---|
| | | |
| | | |
| | | |
Site Visit Checklist
| Task | Done | Notes |
|---|
| Verify all network drops | [ ] | |
| WiFi mapping per building | [ ] | |
| Confirm IT office location and access | [ ] | |
| Confirm IT trailer location | [ ] | |
| Confirm PRInfo display locations | [ ] | |
| Confirm badge booth location | [ ] | |
| Confirm prize area for cameras | [ ] | |
| Confirm hospitality/meals station location | [ ] | |
| Note any issues for Brian Chee (fairgrounds IT) | [ ] | |
Tuesday, February 10 — IT Trailer Setup & Staging
Time: ~1 PM
Crew: Mike, Todd, David, Chris(?), Dean
Set up IT trailer with computer and printer. Stage and test all Raspberry Pis. Test hospitality scanner. Set up cameras and switch for Prize/Info.
Afternoon — IT Trailer & Office
| Task | Done | By | Notes |
|---|
| Set up Windows computer with dual monitors | [ ] | | |
| Start Docker monitoring stack | [ ] | | |
| Verify Uptime Kuma, Grafana, Prometheus running | [ ] | | |
| Connect to network | [ ] | | |
| Verify Tailscale VPN connected | [ ] | | |
| Set up printer | [ ] | | |
Afternoon — Pi Staging & Testing
Set up local switch and separate TV to test each Pi individually before deployment.
| Pi | Boots OK | Network OK | Content Displays | Verified By | Notes |
|---|
| prinfo1 | [ ] | [ ] | [ ] | | |
| prinfo2 | [ ] | [ ] | [ ] | | |
| prinfo3 | [ ] | [ ] | [ ] | | |
| prinfo4 | [ ] | [ ] | [ ] | | |
Afternoon — Hospitality Scanner
| Task | Done | By | Notes |
|---|
| Samsung tablet powered on | [ ] | | |
| Connect USB barcode scanner | [ ] | | |
| Connect to WiFi | [ ] | | |
| Load meals.hamcation.com in Chrome | [ ] | | |
| Test badge scanning end-to-end | [ ] | | |
Afternoon — Camera & Switch Setup
| Task | Done | By | Notes |
|---|
| Set up network switch for Prize/Info area | [ ] | | |
| Connect UCG-Max console | [ ] | | |
| Connect Camera 1 via UACC-PoE+-USBC | [ ] | | |
| Connect Camera 2 via PoE injector | [ ] | | |
| Verify cameras recording in UniFi Protect | [ ] | | |
| Connect UPS battery backup | [ ] | | |
| Verify remote access via unifi.ui.com | [ ] | | |
Afternoon — RV AP Setup
| Task | Done | By | Notes |
|---|
| Configure TP-Link router/AP for RV area | [ ] | | |
| Verify WiFi coverage at RV check-in | [ ] | | |
| Test POS connectivity | [ ] | | |
Wednesday, February 11 — Display Setup
Time: ~7 AM
Crew: Mike, Todd, David, Chris, Dean, Ray Walker
Equipment was delivered Monday (hands-off). Set up TVs and Pis at all locations. Verify hospitality scanner. Set up Starlink for Testing. Ticket booth POS and AP setup in the afternoon.
Morning — Inventory & Verify Delivery
| Task | Done | By | Time | Notes |
|---|
| Verify TVs and accessories at IT office | [ ] | | | |
| Verify TP-Link routers received | [ ] | | | |
| Verify Starlink equipment received | [ ] | | | |
| Verify stands delivered to each building | [ ] | | | |
| Inventory all delivered items | [ ] | | | |
Morning — PRInfo Display Installation
Install at each location as soon as TVs and stands are available. See the PRInfo Display Setup Guide for detailed steps with photos.
| Display | Location | Stand Ready | TV Mounted | Pi Connected | HDMI OK | Network OK | Content Showing | Done By | Notes |
|---|
| PRInfo 1 | Prize & Info (Booth 191) | [ ] | [ ] | [ ] | [ ] | [ ] | [ ] | | |
| PRInfo 2 | Swaps building | [ ] | [ ] | [ ] | [ ] | [ ] | [ ] | | |
| PRInfo 3 | East Hall | [ ] | [ ] | [ ] | [ ] | [ ] | [ ] | | |
| PRInfo 4 | West Hall | [ ] | [ ] | [ ] | [ ] | [ ] | [ ] | | |
Morning — Hospitality Handoff
| Task | Done | By | Time | Notes |
|---|
| Set up Samsung tablet at meals location | [ ] | | | |
| Connect barcode scanner and power | [ ] | | | |
| Connect to WiFi | [ ] | | | |
| Test meals.hamcation.com end-to-end | [ ] | | | |
| Hand off to Hospitality committee | [ ] | | | |
Afternoon — Starlink Setup
Location: Children’s Safety Village
This year: Set up pipe at Safety Village to make future setup easier.
| Task | Done | By | Time | Notes |
|---|
| Transport Starlink equipment to Safety Village | [ ] | | | |
| Set up pipe for dish mounting (2026 only) | [ ] | | | |
| Mount dish with clear sky view | [ ] | | | |
| Connect router and power | [ ] | | | |
| Wait for satellite connection | [ ] | | | |
| Verify internet connectivity | [ ] | | | |
| Test speed (expect 30–170 Mbps down) | [ ] | | | |
| Confirm WiFi SSID: HamCationSL | [ ] | | | |
| Hand off to Testing Committee | [ ] | | | |
Afternoon — Ticket Booth POS Setup
| Booth | TP-Link Connected | POS Device Connected | Transaction Test OK | Done By | Notes |
|---|
| [ ] | [ ] | [ ] | | |
| [ ] | [ ] | [ ] | | |
| [ ] | [ ] | [ ] | | |
| [ ] | [ ] | [ ] | | |
Afternoon — Ticket Booth AP Setup
| Task | Done | By | Notes |
|---|
| Deploy AP at ticket booth location(s) | [ ] | | |
| Verify WiFi coverage for POS devices | [ ] | | |
| Test connectivity end-to-end | [ ] | | |
End of Day Checklist
| Task | Done | Notes |
|---|
| All 4 PRInfo displays showing content | [ ] | |
| Hospitality scanner verified working | [ ] | |
| Starlink running and handed off | [ ] | |
| Ticket booth POS verified working | [ ] | |
| Ticket booth AP coverage confirmed | [ ] | |
| All equipment secured overnight | [ ] | |
| Golf cart parked at IT trailer | [ ] | |
| Brief Thursday crew on status | [ ] | |
Thursday, February 12 — Final Verify
Time: ~6 AM
Crew: Mike, Todd, David, Chris, Dean
Full systems verification of all equipment. Swaps loads in today.
Morning — Full Systems Verification
| System | Location | Working | Verified By | Notes |
|---|
| PRInfo 1 | Prize & Info (Booth 191) | [ ] | | |
| PRInfo 2 | Swaps building | [ ] | | |
| PRInfo 3 | East Hall | [ ] | | |
| PRInfo 4 | West Hall | [ ] | | |
| Badge printer (Pi) | [ ] | | | |
| Badge printer (backup laptop) | [ ] | | | |
| Surveillance Camera 1 | [ ] | | | |
| Surveillance Camera 2 | [ ] | | | |
| Meals tablet + scanner | [ ] | | | |
| IT Ops computer + monitoring | [ ] | | | |
| Starlink at Safety Village | [ ] | | | |
| Ticket booth POS (all) | [ ] | | | |
| RV TP-Link router | [ ] | | | |
| Golf cart at IT trailer | [ ] | | | |
End of Day Checklist
| Task | Done | Notes |
|---|
| All systems verified | [ ] | |
| Brief Friday morning crew | [ ] | |
| Confirm Friday volunteer arrival times (6 AM) | [ ] | |
| Equipment secured overnight | [ ] | |
| Golf cart parked, keys secured | [ ] | |
Friday, February 13 — Event Day 1
Time: ~6 AM (Gates open 9 AM, close 5 PM)
Crew: Mike, Todd, David, Chris, Dean, Jacob
First day — expect more issues as systems run under full load.
Early AM — Morning Opening
| Task | Done | By | Time | Notes |
|---|
| Pick up radios from Security Office | [ ] | | | |
| IT Operations room open and staffed | [ ] | | | |
| Monitoring dashboards running | [ ] | | | |
| Golf cart at IT trailer, keys accounted for | [ ] | | | |
| Verify PRInfo 1 — Prize & Info (Booth 191) | [ ] | | | |
| Verify PRInfo 2 — Swaps building | [ ] | | | |
| Verify PRInfo 3 — East Hall | [ ] | | | |
| Verify PRInfo 4 — West Hall | [ ] | | | |
| Badge printing booth operational | [ ] | | | |
| Test print successful | [ ] | | | |
| Surveillance cameras recording | [ ] | | | |
| Meals station ready | [ ] | | | |
| Ticket booth POS verified | [ ] | | | |
| Radio check all positions | [ ] | | | |
During Event — Periodic Checks
- Busiest day for badge reprints (lost badges)
- Vendor WiFi requests peak
- Monitor all systems closely — first full-load day
- Watch for network congestion
Evening — Closing
| Task | Done | By | Time | Notes |
|---|
| Verify all 4 PRInfo displays running | [ ] | | | |
| Note badge paper supply level | [ ] | | | |
| Return radios to Security Office | [ ] | | | |
| Golf cart parked at IT trailer | [ ] | | | |
| IT Operations room locked | [ ] | | | |
| Brief Saturday morning crew | [ ] | | | |
Saturday, February 14 — Event Day 2
Time: ~6 AM (Gates open 9 AM, close 5 PM)
Crew: Mike, Todd, David, Dean, Jacob, Patrick Gee
Peak attendance day — highest volume. Chris is not available today.
Early AM — Morning Opening
| Task | Done | By | Time | Notes |
|---|
| Pick up radios from Security Office | [ ] | | | |
| IT Operations room open and staffed | [ ] | | | |
| Monitoring dashboards running | [ ] | | | |
| Golf cart at IT trailer, keys accounted for | [ ] | | | |
| Verify PRInfo 1 — Prize & Info (Booth 191) | [ ] | | | |
| Verify PRInfo 2 — Swaps building | [ ] | | | |
| Verify PRInfo 3 — East Hall | [ ] | | | |
| Verify PRInfo 4 — West Hall | [ ] | | | |
| Badge printing booth operational | [ ] | | | |
| Surveillance cameras recording | [ ] | | | |
| Meals station ready | [ ] | | | |
| Review Friday issues | [ ] | | | |
| Radio check all positions | [ ] | | | |
Afternoon — Starlink Teardown
Testing finishes ~2 PM. Coordinate with Testing Committee.
| Task | Done | By | Time | Notes |
|---|
| Confirm with Testing Committee that testing is complete | [ ] | | | |
| Cap the pipe at Safety Village | [ ] | | | |
| Power down Starlink equipment | [ ] | | | |
| Pack dish, router, cables | [ ] | | | |
| Transport back to IT office | [ ] | | | |
Evening — Closing & TP-Link Collection
| Task | Done | By | Time | Notes |
|---|
| Verify all 4 PRInfo displays running | [ ] | | | |
| Collect TP-Link routers from closed ticket booths | [ ] | | | |
| Return radios to Security Office | [ ] | | | |
| Golf cart parked at IT trailer | [ ] | | | |
| IT Operations room locked | [ ] | | | |
| Brief Sunday morning crew | [ ] | | | |
| Identify equipment for early teardown staging | [ ] | | | |
Sunday, February 15 — Event Day 3 & Teardown
Time: ~7 AM (Gates open 9 AM, close 1 PM)
Crew: Mike, Todd, David, Chris, Dean, Jacob, Patrick Gee
Shorter day — transitions to teardown after 1 PM close.
Early AM — Morning Opening
| Task | Done | By | Time | Notes |
|---|
| Pick up radios from Security Office | [ ] | | | |
| IT Operations room open and staffed | [ ] | | | |
| Monitoring dashboards running | [ ] | | | |
| Golf cart at IT trailer, keys accounted for | [ ] | | | |
| Verify PRInfo 1 — Prize & Info (Booth 191) | [ ] | | | |
| Verify PRInfo 2 — Swaps building | [ ] | | | |
| Verify PRInfo 3 — East Hall | [ ] | | | |
| Verify PRInfo 4 — West Hall | [ ] | | | |
| Badge printing booth operational | [ ] | | | |
| Surveillance cameras recording | [ ] | | | |
| Meals station ready | [ ] | | | |
| Pick up RV TP-Link router | [ ] | | | |
| Radio check all positions | [ ] | | | |
Afternoon — Teardown Phase 1: PRInfo Displays
After 1 PM close — wait for official word from HamCation Operations.
Use golf cart to transport equipment back to IT trailer. Farthest displays first.
| Display | Location | Pi Off | Cables Out | TV Off Stand | Packed | At Staging | Done By |
|---|
| PRInfo 4 | West Hall | [ ] | [ ] | [ ] | [ ] | [ ] | |
| PRInfo 3 | East Hall | [ ] | [ ] | [ ] | [ ] | [ ] | |
| PRInfo 2 | Swaps building | [ ] | [ ] | [ ] | [ ] | [ ] | |
| PRInfo 1 | Prize & Info (Booth 191) | [ ] | [ ] | [ ] | [ ] | [ ] | |
Afternoon — Teardown Phase 2: Badge Printing
| Task | Done | By | Notes |
|---|
| Complete final badge requests | [ ] | | |
| Power off printer and Pi | [ ] | | |
| Pack printer, Pi, laptop, cables | [ ] | | |
| Secure remaining badge paper | [ ] | | |
Afternoon — Teardown Phase 3: Surveillance
| Task | Done | By | Notes |
|---|
| Download any needed footage | [ ] | | |
| Power off UCG-Max | [ ] | | |
| Remove cameras | [ ] | | |
| Pack console, UPS, cameras, PoE adapters | [ ] | | |
Afternoon — Teardown Phase 4: Hospitality
| Task | Done | By | Notes |
|---|
| Power off Samsung tablet | [ ] | | |
| Pack tablet, scanner, cables | [ ] | | |
Afternoon — Teardown Phase 5: TP-Link Routers
| Task | Done | By | Notes |
|---|
| Collect all remaining TP-Link routers | [ ] | | |
| Pack routers and cables | [ ] | | |
Afternoon — Teardown Phase 6: IT Ops Room (Last)
| Task | Done | By | Notes |
|---|
| Stop Docker monitoring stack | [ ] | | |
| Power off Windows computer | [ ] | | |
| Pack computer, monitors, cables | [ ] | | |
| Collect all documentation and logs | [ ] | | |
| Return radios to Security Office | [ ] | | |
| Clear room of all IT equipment | [ ] | | |
Final Inventory
| Item | Present | Condition | Notes |
|---|
| PRInfo Kit 1 (TV, stand, Pi, cables) | [ ] | | |
| PRInfo Kit 2 (TV, stand, Pi, cables) | [ ] | | |
| PRInfo Kit 3 (TV, stand, Pi, cables) | [ ] | | |
| PRInfo Kit 4 (TV, stand, Pi, cables) | [ ] | | |
| Badge Raspberry Pi + cables | [ ] | | |
| Laser printer + toner | [ ] | | |
| Windows laptop | [ ] | | |
| Badge template paper (remaining) | [ ] | | |
| UCG-Max console + UPS | [ ] | | |
| Camera 1 + mount hardware | [ ] | | |
| Camera 2 + PoE injector | [ ] | | |
| Samsung tablet + scanner | [ ] | | |
| Windows computer + monitors | [ ] | | |
| TP-Link WiFi APs (x4) | [ ] | | |
| Starlink (dish, router, cable) | [ ] | | |
| Extension cords | [ ] | | |
| Power strips | [ ] | | |
| Ethernet cables | [ ] | | |
| HDMI cables | [ ] | | |
| Golf cart keys → return to Mike Beers | [ ] | | |
| Task | Done | By | Notes |
|---|
| All equipment checked against inventory | [ ] | | |
| Damaged/missing items documented | [ ] | | |
| Equipment loaded for transport to storage | [ ] | | |
| Golf cart keys returned to Mike Beers (Chair) | [ ] | | |
| Storage secured | [ ] | | |